03.2400 Reporting
by Brands · 9 things on Twos
- Analyse the Epic Burndown Chart for one of your teams epics
- Which two facts can you definitely conclude?
- INCORRECT! There are 6 more sprints predicted for this epic but we dont know the duration of those sprints.
- CORRECT! Since work started 6 story points have been added to the Epic
- INCORRECT! 13% of issues were unestimated
- INCORRECT! We have no idea from this report the number of issues are in the epic, we just know theres 21 story points estimated in the epic
- CORRECT! 9 story points have been completed in this Epic so far
- INCORRECT! We don't know if more story points will be added to the epic