01.2225 Managing projects
by Brands · 8 things on Twos
- Certain scrum masters must be able to create and reorder sprints in a particular project
- Identify three possible actions that may enable them to do so
- CORRECT! Group is a valid entry in a permission scheme and so this action would satisfy the requirement if the Scrum Masters are in a group listed in Manage sprints permission
- CORRECT! Project role is a valid entry in a permission scheme to Manage sprints
- INCORRECT! App access is a valid entry in permission scheme but Jira Core users cannot access features of a Jira software project like the boards in order to manage sprints.
- CORRECT! Admins project role may be listed in Manage sprints permission, its not always true but is a possible action.
- INCORRECT! Making them board admins does not grant them Manage Sprints permission.
- INCORRECT! Schedule issues permission allows users to add issues to sprints and edit them but not to manage sprints.