Wed May 04, 2022 - A505 Hong Kong Project Daily Log
by dave2963@ · 7 things on Twos
- Wed May 04, 2022 - A505 - Site Visit (am) with Harry
- Wed May 04, 2022 - A505 - Site Visit (pm) with Vinil re handover
- Wed May 04, 2022 - A505 - Weekly BIM Review Meeting
- Received signed DCC for Granulation Building from Valerie, spoke to Beth and arranged for her to prepare the letter for submitting to the ER - Beth sent the letter through
- ✓ Follow up - Received signed DCC for Granulation Building from Valerie, spoke to Beth and arranged for her to prepare the letter for submitting to the ER - Beth sent the letter through
- Email to Emma, Tomal, Scott, Prominent confirming week 38 shipping would be OK for the polymer system and chasing up the data sheets
- Email to Vinil, JEC, with most recent Civil Guidance for the Reception Building Rev 14 for the Ground Floor, including the plinths for the crane platform. Also attached Rev 7 for the basement